This article is for maintenance managers, plant managers and production managers who report an MTTR every month without knowing what to do with it. A single MTTR blends three durations that have different causes and different levers: the wait before repair starts, the repair itself and the restart. We focus here on the first, often the longest and the least measured, and on how to calculate it from the real start and end of every stop as seen by the machine.
- One MTTR blends waiting, repair and restart.
- Waiting time starts when the machine stops.
- The CMMS timestamps requests, the machine timestamps stops.
- The distribution of waiting time shows where to act.
What Huoltu explains about MTTR and its scope
In the French article MTBF et MTTR : les indicateurs clés de la maintenance industrielle (MTBF and MTTR: the key indicators of industrial maintenance), Huoltu presents both indicators, their formulas, the availability calculation, improvement levers and common interpretation traps. On MTTR, the article flags a point that is often overlooked: “Le MTTR peut inclure ou exclure l’attente de pièces, la mobilisation du technicien, le diagnostic initial” (“MTTR may include or exclude waiting for parts, technician mobilization, the initial diagnosis”).
Huoltu defines MTTR as the time between the detection of a failure and the equipment’s actual return to production, notes that ISO 14224 separates active repair time from total downtime, and lists the steps to shorten: detection, diagnosis, spare parts and standardized repair procedures. The article also recommends automated data collection, with a CMMS that timestamps when each request is created, assigned and closed. For definitions, formulas and maintenance-side levers, read the original article. Our starting point is its warning on scope: if MTTR may or may not include the wait, that wait has to be measured on its own.
One MTTR, three durations: waiting, repair, restart
A breakdown stop splits into three consecutive segments:
- Waiting time before repair: from the moment the machine stops to the moment repair work starts. It contains the time before the request (the stop goes unnoticed, or the call goes out late) and the mobilization time (the technician finishes another job, walks over, looks for tools).
- Repair: diagnosis, any wait for parts, the repair itself and testing.
- Restart: from the end of the repair to the moment the machine is actually running again.
An example to make this concrete, with no real data: two lines both show an MTTR of 90 minutes. On the first, 60 minutes of waiting, 25 minutes of repair and 5 minutes of restart. On the second, 15 minutes of waiting, 70 minutes of repair and 5 minutes of restart. The same figure calls for two opposite action plans: organization and alerting for the first, diagnosis, parts and procedures for the second. Until MTTR is broken down, you cannot tell which case you are in.
What the machine sees, what the CMMS sees
Breaking a stop down takes five timestamps. Two of them are only known precisely by the machine:
| Timestamp | Most reliable source | What it lets you calculate |
|---|---|---|
| Start of the stop | Machine, automatic timestamp | Starting point of the wait and of total stop time |
| Repair request | CMMS (request created) or phone call | Time before the request |
| Start of repair | CMMS (request taken) or entry at the workstation | Mobilization time, end of the wait |
| End of repair | CMMS (request closed) | Repair duration |
| Machine running again | Machine, automatic timestamp | Restart and total stop time |
A CMMS that timestamps its requests provides the three middle timestamps. Without timestamping at the machine, the first and the last are reconstructed from memory, and the time before the request simply disappears: it starts before anyone has opened a request. On the quality of these timestamps, see Reliable MTBF data: timestamping every stop automatically at the machine.
Reading waiting time by shift, by hour and by failure type
A monthly average wait says little. Its distribution shows where to act. A few common patterns, to check against your own data:
| What the data shows | Likely cause | Lever |
|---|---|---|
| Long time before the request, short mobilization | The stop is not seen, the operator is at another station, the call goes out late | Automatic alert beyond a stop duration, written call rule |
| Long mobilization during the day | Technicians busy, unclear priorities between requests | Priority by machine criticality, visible request queue |
| Long wait at night or at weekends | On-call coverage, missing skills on the shift | On-call organization, first-level repairs by operators |
| Wait concentrated on one failure type | Rare skill, specific tooling | Training, written procedure, tooling kept close to the machine |
| Short wait, long repair | Diagnosis, parts, no procedure | Maintenance levers described by Huoltu: documentation, stock, procedures |
Look at the median and the longest stops as well as the average: a handful of waits lasting several hours is enough to push MTTR up, and the same time slots often come back. The different ways of defining MTTR itself are compared in What is MTTR and which of the four MTTR variants do you actually want?
Measuring waiting time before repair in five steps
- Write the convention down. As Huoltu points out, MTTR scope varies from one team to another. Set where each segment starts and ends, and where waiting for parts belongs (inside the repair, tracked separately).
- Timestamp the start and end of every stop at the machine. Night shifts included, and breakdowns of only a few minutes too.
- Link every breakdown stop to its repair request. One machine stop, one main request: flag stops without a request and requests without a stop.
- Calculate the three segments and their distribution. By machine, by shift, by time slot and by failure type, as an average and as a median.
- Act on the dominant segment, then track it. Set a waiting time target per criticality level from the baseline measurement, and check month after month that the wait goes down without the repair getting longer.
The restart deserves its own tracking, especially after a long stop: see After the restart: why a lower MTTR does not always add parts, and how to measure recovery loss in OEE.
The role of TEEPTRAK
TEEPTRAK measures the state of every machine automatically: a module wired into the electrical cabinet and a sensor at the line, about one hour of installation per machine, no connection to the PLC, and a first OEE within 48 hours. The start and end of every stop are timestamped at the machine, and the operator enters the cause at the workstation. Matched with the requests in your CMMS, these timestamps give the waiting time before repair, the repair duration and the restart, stop by stop. TEEPTRAK is not an MES and does not replace your CMMS: it provides the timestamps that only the machine knows. It is used in more than 700 plants in more than 30 countries.
Further reading
- MTBF et MTTR : les indicateurs clés de la maintenance industrielle (Huoltu, in French)
- From fault report to availability: which downtime data maintenance in mid-sized plants really needs
- After the restart: why a lower MTTR does not always add parts, and how to measure recovery loss in OEE
FAQ
Is waiting time before repair part of MTTR? It depends on the convention you choose, and Huoltu notes that teams do not all set it the same way. The most useful approach is to track MTTR over the total machine stop time, then break it down into waiting, repair and restart.
How is it different from MTTA? MTTA measures how long it takes to acknowledge an alert. Waiting time before repair goes further: it starts at the real beginning of the stop, before any alert or request exists, and ends when repair work actually starts.
Should we set a waiting time target? Yes, but per criticality level and from a baseline measured over a few weeks. A single target for every machine encourages fast handling of easy stops at the expense of bottleneck machines.