This article is for production planners, production managers, plant managers, continuous improvement leads and maintenance managers who promise customers a delivery date and see that promise slip too often. It is not about the planning model itself. It is about what causes the spread in daily output: downtime and micro-stops on each machine. You will read why the average is not enough, which kinds of stops inflate the safety time, and how measured downtime data lets you work on the source of that spread instead of simply making the buffer bigger.
- The average sets the waiting time, the spread sets the safety time.
- Long breakdowns create the worst days.
- Micro-stops lower output without reaching the logbook.
- Less spread at the source means a shorter delivery promise.
What Sirris writes about calculating delivery dates from the workload
In the Dutch article Bereken leverdata met uw werkvoorraad (“Calculate delivery dates with your workload”, Sirris, 28 October 2026), Pascal Pollet, Principal Engineer Manufacturing Strategy at Sirris, the collective centre of the Belgian technology industry, explains how to derive a delivery date from the current workload instead of a fixed lead time. The expected waiting time is the open workload divided by realistic average output; processing time and a safety time are added on top. On working with an average output, he writes: “Dat maakt de berekening eenvoudig en transparant, maar verbergt de dagelijkse schommelingen in de productie” (“That makes the calculation simple and transparent, but hides the daily fluctuations in production.”)
Sirris bases realistic output on the actual throughput of recent weeks or months, not on the theoretical capacity of the machines, and recommends recalculating after structural changes such as an extra shift or an extra machine. The safety time follows from the delivery reliability you want to reach and from the historical differences between predicted and actual lead times. The article names breakdowns, material shortages, quality problems and absences as reasons why daily output is never constant, treats rush orders as a separate priority class, and announces a next part using a Monte Carlo simulation of daily output. For the method itself, read his article. We start from a different question: where does the spread in daily output come from, and what can you do about it on the shop floor?
Why the average is not enough: the spread sets the safety time
Two lines can have the same average output and still need a very different delivery promise. Take, as an illustration rather than a measurement, two lines that each make 400 parts per day on average. Line A makes between 370 and 430 parts almost every day. Line B reaches 470 parts on good days, but drops to 250 a few times a month because of a long breakdown, and on other days loses an hour to short stops that nobody writes down. With the same workload, the calculation gives both lines the same expected waiting time. To reach the same delivery reliability, however, line B needs a much larger safety time, because its actual lead times stray further from the forecast.
The average and the spread therefore call for two different actions. A higher average output shortens the expected waiting time. Less spread shrinks the safety time. If you only look at the average, you miss the second effect, and that effect is exactly what decides how many days you add on top of the calculation.
The throughput history shows the result for each day, not the cause. A bad day appears in the figures as 250 parts, not as two hours of breakdown on the press and forty minutes of micro-stops on the packaging machine. To reduce the spread, you need to know that cause for each machine.
Which stops make daily output fluctuate
Not every stop affects the spread in the same way. The pattern (how often, how long, how predictable) decides whether a loss mainly lowers the average or mainly creates the worst days.
| Type of loss | Typical pattern | Effect on daily output | What you measure per machine |
|---|---|---|---|
| Long breakdown | Rare, but hours each time | A few very bad days: the tail that sets the safety time | Start, end and cause of every breakdown |
| Repeated short breakdowns | Several times per shift, a few minutes each | Uneven days, depending on product or shift | Number and duration per day, per shift and per product |
| Micro-stops | Dozens of times a day, a few seconds to a minute | Lower output with no recorded stop, varying with product, material and settings | Frequency and total duration per day, below a fixed threshold |
| Changeovers | Planned, but with varying duration | Predictable once the real duration per product is known | Real duration of each changeover, including ramp-up |
| Waiting for material or operator | Cause outside the machine | Bad days that are not due to the machine | Stop with reason “waiting”, separate from breakdowns |
| Speed loss | Machine runs slower than the reference | Constant or creeping drop | Actual cycle time next to the reference cycle time |
Two points stand out. Long breakdowns mainly create the worst days, and therefore drive the safety time when you aim for high delivery reliability. Micro-stops mainly lower the average, but they fluctuate too: for example, 60 micro-stops of 40 seconds cost 40 minutes on one day, and on a day with a harder product or poorer material that can double. Because micro-stops are rarely recorded by hand, those days appear in the throughput history as unexplained bad days.
Sirris notes that the method works best when material is available. Stops caused by waiting for material therefore belong in a separate category in the data: they have a different cause, and a different owner, than a breakdown on the machine.
Method: reducing the spread at the source
- Choose the machine that sets the throughput. This is usually the bottleneck of the routing for which you calculate delivery dates. Every minute lost there never comes back as output.
- Measure stops and micro-stops automatically for a few weeks. Record the start and end of every stop, short ones included, with a fixed threshold between micro-stop and stop. Let the operator choose the reason for longer stops at the machine.
- Put daily output next to stop minutes per day. Find the worst days of the period and check which stops explain them: one long breakdown, a series of short breakdowns, a peak in micro-stops, or waiting for material.
- Separate predictable from unpredictable spread. Changeovers and planned maintenance can be scheduled once their real duration is measured. Breakdowns and micro-stops are the spread that the safety time has to absorb.
- Tackle the biggest source. For example, the recurring breakdown behind the worst days, or the micro-stops at one station. After the action, check whether the worst days become less bad, not only whether the average goes up.
- Recalculate the safety time. Use recent throughput and the new differences between predicted and actual lead times, following the Sirris method. You then see in days what the shop floor improvement brings to the delivery promise.
The order matters: without step 2, steps 3 to 5 remain a discussion about memories. With measured stops, it becomes a discussion about facts, machine by machine.
What TEEPTRAK measures, and what it does not do
TEEPTRAK automatically measures the state of every machine: a module in the electrical cabinet and a sensor at the line, about one hour of installation per machine, no PLC connection, and a first OEE within 48 hours. Every stop and every micro-stop is recorded with its start and end, the operator chooses the reason at the machine, and output per day, per shift and per product sits next to the stops that explain it. TEEPTRAK does not calculate delivery dates and is not an MES or a planning system: the calculation from workload and output stays with your planning team. TEEPTRAK provides the measured downtime data that explains and reduces the spread in that output. It is used in more than 700 plants in more than 30 countries.
Further reading
- Bereken leverdata met uw werkvoorraad (Sirris, Pascal Pollet, in Dutch)
- Delivery dates and shop floor reality: why production planning needs measured machine availability
- Downtime spike: real signal or noise? Control chart rules for daily stops and scrap
FAQ
Should I cut the safety time as soon as downtime goes down? Not straight away. Let the lower spread show up for a few weeks in throughput and in the differences between predicted and actual lead times, then recalculate. A shorter promise based on one good week puts your delivery reliability at risk.
Why do micro-stops matter if they last only a few seconds? Because they happen often and vary from day to day. Together they can cost many minutes per shift, and they lower output without any stop appearing in the logbook. Without automatic measurement, that loss only shows up as an unexplained bad day.
Does this work if I only have the throughput history? Yes. The Sirris calculation starts from actual throughput and does not need downtime data. Downtime data per machine does not change the calculation, but it shows where the spread comes from, so you can reduce it instead of only absorbing it.