{"id":165950,"date":"2026-11-25T08:39:31","date_gmt":"2026-11-25T08:39:31","guid":{"rendered":"https:\/\/teeptrak.com\/corrective-preventive-maintenance-downtime-cost-per-asset\/"},"modified":"2026-11-25T08:39:31","modified_gmt":"2026-11-25T08:39:31","slug":"corrective-preventive-maintenance-downtime-cost-per-asset","status":"publish","type":"post","link":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/","title":{"rendered":"Corrective or preventive maintenance? Measure downtime cost per asset first"},"content":{"rendered":"<p>[et_pb_section fb_built=&#8221;1&#8243; _builder_version=&#8221;4.27&#8243;][et_pb_row][et_pb_column type=&#8221;4_4&#8243;][et_pb_text]<\/p>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">This article is for maintenance managers, engineering teams, plant managers and production managers who have to decide, asset by asset, whether to run corrective or preventive maintenance. You know the trade-off between criticality, downtime cost and safety. This article deals with the criterion that most often rests on an estimate: downtime cost. It explains which downtime data you need for each asset, how to measure it rather than guess it, and how to turn it into a strategy per asset that you can review later.<\/p>\n<div style=\"background:#f7f5f3;border-left:4px solid #EB352B;border-radius:6px;padding:20px 24px;margin:24px 0 32px;\">\n<div style=\"font-size:15px;font-weight:bold;color:#232120;margin-bottom:10px;text-transform:uppercase;letter-spacing:1px;\">In short<\/div>\n<ul style=\"font-size:16px;line-height:1.7;color:#232120;margin:0;padding-left:20px;\">\n<li style=\"margin-bottom:6px;\">Downtime cost is hours times an hourly rate; the hours are usually estimated.<\/li>\n<li style=\"margin-bottom:6px;\">Short stops and restarts are missing from logs and work orders.<\/li>\n<li style=\"margin-bottom:6px;\">Downtime measured per asset makes the choice defensible.<\/li>\n<li style=\"margin-bottom:6px;\">The same measurement shows later whether the strategy works.<\/li>\n<\/ul>\n<\/div>\n<h2 style=\"color:#232120;font-size:28px;margin-top:40px;margin-bottom:20px;\">What DTS Mechanical says about corrective and preventive maintenance<\/h2>\n<blockquote style=\"border-left:5px solid #232120;background:#f7f5f3;margin:28px 0;padding:20px 26px;font-size:19px;line-height:1.7;color:#232120;font-style:normal;\"><p>In the article <a href=\"https:\/\/dts-mechanical.be\/correctief-onderhoud-vs-preventief-onderhoud-welke-strategie-past-bij-uw-bedrijf\/\" target=\"_blank\" rel=\"noopener\">Correctief Onderhoud vs Preventief Onderhoud: Welke Strategie Past bij Uw Bedrijf?<\/a> (in Dutch: &#8220;Corrective vs preventive maintenance: which strategy suits your business?&#8221;), DTS Mechanical, a Belgian industrial mechanical maintenance specialist, compares the two strategies for production environments such as food processing and port logistics. When choosing a strategy for a production environment, the article names three factors: criticality, downtime cost and safety. On downtime cost, it gives a short, clear instruction: &#8220;Bereken wat een uur productieverlies uw bedrijf kost.&#8221; (&#8220;Calculate what one hour of lost production costs your business.&#8221;)<\/p><\/blockquote>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">DTS Mechanical describes corrective maintenance as repairing equipment after it fails, suited to non-critical equipment, cheap parts that are quick to replace, back-up systems and equipment due for replacement soon. Preventive maintenance relies on inspections, cleaning, lubrication and part replacement at fixed intervals, and requires an investment in planning, administration, trained staff and critical spare parts. According to the article, most industrial companies combine both, and mandatory inspections of lifting equipment, pressure systems and gas-fired installations rule out a purely corrective approach. The article proposes a six-step process, from an equipment inventory to regular monitoring and evaluation, and presents predictive maintenance (vibration, thermography, oil analysis) as a third option. For that strategic trade-off, read the article itself. Here we focus on one step: basing downtime cost per asset on measurement rather than on an estimate.<\/p>\n<h2 style=\"color:#232120;font-size:28px;margin-top:40px;margin-bottom:20px;\">Why downtime cost per asset is often still an estimate<\/h2>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">Downtime cost is an hourly rate multiplied by a number of hours. The hourly rate is usually set fairly reliably by finance: lost output, labor still paid, energy, restart. The hours are the weak point. In many plants they come from the breakdown log, the work orders in the maintenance system or the shift&#8217;s memory, with four consequences:<\/p>\n<ul style=\"margin:0 0 20px 0;padding-left:24px;\">\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>Only the big breakdowns count.<\/strong> A two-hour breakdown goes into the log; ten five-minute stops that the operator clears alone usually do not. Yet together they can cost as much production time.<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>The work order measures the repair, not the downtime.<\/strong> The time between the stop and the call, and the restart after the repair, are often missing.<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>Cost is estimated per line, the decision is made per asset.<\/strong> Whether a pump, a conveyor or a cutting machine gets preventive maintenance requires figures per asset, not a line average.<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>Knock-on downtime stays out of sight.<\/strong> A breakdown on a machine feeding the bottleneck costs more than the same breakdown on a machine with a buffer. Without measurement at the bottleneck, you cannot see the difference.<\/li>\n<\/ul>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">The result: the asset that gets talked about the most receives the most intensive preventive program, even when another asset costs more production time.<\/p>\n<figure style=\"margin:32px 0;\"><img decoding=\"async\" src=\"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/11\/teeptrak-dts-en.png\" alt=\"Four-step diagram for choosing corrective or preventive maintenance per asset based on measured downtime cost\" width=\"1600\" height=\"900\" style=\"width:100%;height:auto;border-radius:8px;\" loading=\"lazy\" \/><\/figure>\n<h2 style=\"color:#232120;font-size:28px;margin-top:40px;margin-bottom:20px;\">Which downtime data you need for each asset<\/h2>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">A single number is not enough to choose between corrective and preventive. These data points together give a usable picture, measured over at least a few weeks on every asset you want to classify:<\/p>\n<table style=\"width:100%;border-collapse:collapse;margin:24px 0;font-size:15px;\">\n<thead>\n<tr>\n<th style=\"background:#232120;color:#fff;padding:10px;text-align:left;border:1px solid #ddd;\">Data per asset<\/th>\n<th style=\"background:#232120;color:#fff;padding:10px;text-align:left;border:1px solid #ddd;\">Why it matters for the choice<\/th>\n<th style=\"background:#232120;color:#fff;padding:10px;text-align:left;border:1px solid #ddd;\">What happens if you estimate it<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Unplanned downtime hours per month<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Basis of downtime cost (hours times hourly rate)<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Short stops drop out, cost looks lower than it is<\/td>\n<\/tr>\n<tr>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Number of stops (frequency)<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Many short stops call for a different approach than a few long breakdowns<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">The pattern is invisible, everything looks like one type of failure<\/td>\n<\/tr>\n<tr>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Average and longest stop duration<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Long breakdowns point to spare parts, redundancy or a preventive approach<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">One spectacular breakdown shapes the picture<\/td>\n<\/tr>\n<tr>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Position relative to the bottleneck<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Downtime at the bottleneck is lost output for the whole line<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Every stop gets the same weight<\/td>\n<\/tr>\n<tr>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Duration of planned maintenance<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">Preventive maintenance also takes production time, to set against the breakdowns it avoids<\/td>\n<td style=\"padding:10px;border:1px solid #ddd;vertical-align:top;color:#232120;\">The cost of the preventive program stays out of the comparison<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">With this data, you calculate downtime cost per asset from what actually happened, and you also see which type of downtime drives that cost.<\/p>\n<h2 style=\"color:#232120;font-size:28px;margin-top:40px;margin-bottom:20px;\">From measured downtime to a strategy per asset<\/h2>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">Here is how to turn the measurement into a decision, in line with the three factors DTS Mechanical names:<\/p>\n<ol style=\"margin:0 0 20px 0;padding-left:24px;\">\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>List the assets<\/strong> you want to classify, and record for each one its criticality for the core process and its safety requirements, including mandatory inspections.<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>Measure downtime per asset<\/strong> over a representative period, for example four weeks: every stop with start, end and cause, short ones included.<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>Calculate downtime cost<\/strong> using your finance team&#8217;s hourly rate times the measured unplanned hours, and give downtime at the bottleneck its own weight.<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>Classify each asset.<\/strong> Critical with high measured cost: preventive, or condition-based if failures give warning signs. Non-critical, low cost and quick to repair: corrective can be justified. Safety or mandatory inspection: preventive, regardless of the cost trade-off.<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>Treat frequent short stops separately.<\/strong> A fixed maintenance interval rarely solves them; they often need a root cause analysis with production first, because setup, materials or operation play a part.<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><strong>Review after a few months<\/strong> with the same measurement: are unplanned stops falling on the assets under preventive maintenance, and do the assets under corrective maintenance stay cheap?<\/li>\n<\/ol>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">An example, for illustration only: a plant believes its packaging machine is its most expensive asset, because its last breakdown lasted half a day. After four weeks of measurement, a conveyor feeding the bottleneck turns out to cost more unplanned hours, spread over dozens of short stops that nobody wrote down. The preventive priority shifts, and the short stops first get a root cause analysis. Our articles on <a href=\"https:\/\/teeptrak.com\/en\/measure-downtime-duration-frequency-cost\/\">measuring downtime duration and frequency<\/a> and on <a href=\"https:\/\/teeptrak.com\/en\/preventive-maintenance-effectiveness-unplanned-stops\/\">preventive maintenance effectiveness<\/a> cover the calculation and the follow-up check in more detail.<\/p>\n<h2 style=\"color:#232120;font-size:28px;margin-top:40px;margin-bottom:20px;\">How TEEPTRAK measures downtime per asset<\/h2>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\">TEEPTRAK measures OEE, downtime and micro-stops on each machine in real time. On each machine, a module is wired into the electrical cabinet and a sensor is fitted at the line, in about an hour, without connecting to the PLC; the first OEE is available within 48 hours. Every stop is recorded with its start and end, short ones included, and the operator assigns the cause at the machine. This gives you, for each asset, the unplanned hours, frequency and duration you need to calculate downtime cost and review the strategy. TEEPTRAK is not an MES, does not replace your maintenance system or maintenance planning, and does not do vibration analysis: it provides the measured downtime data that is missing from the decision and the review. TEEPTRAK is used in more than 700 plants in more than 30 countries.<\/p>\n<h3 style=\"color:#232120;font-size:22px;margin-top:32px;margin-bottom:14px;\">Further reading<\/h3>\n<ul style=\"margin:0 0 20px 0;padding-left:24px;\">\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><a href=\"https:\/\/dts-mechanical.be\/correctief-onderhoud-vs-preventief-onderhoud-welke-strategie-past-bij-uw-bedrijf\/\" target=\"_blank\" rel=\"noopener\">Correctief Onderhoud vs Preventief Onderhoud: Welke Strategie Past bij Uw Bedrijf?<\/a> (DTS Mechanical, in Dutch)<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><a href=\"https:\/\/dts-mechanical.be\/kosten-van-ongeplande-stilstand-productielijnen-de-verborgen-impact-op-uw-bedrijfsresultaat\/\" target=\"_blank\" rel=\"noopener\">Kosten van Ongeplande Stilstand Productielijnen: De Verborgen Impact op Uw Bedrijfsresultaat<\/a> (DTS Mechanical, in Dutch: the hidden cost of unplanned production line downtime)<\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><a href=\"https:\/\/teeptrak.com\/en\/measure-downtime-duration-frequency-cost\/\">Measure downtime duration and frequency before you calculate downtime cost<\/a><\/li>\n<li style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:8px;\"><a href=\"https:\/\/teeptrak.com\/en\/preventive-maintenance-effectiveness-unplanned-stops\/\">Preventive maintenance effectiveness: checking machine by machine whether breakdowns really go down<\/a><\/li>\n<\/ul>\n<h2 style=\"color:#232120;font-size:28px;margin-top:40px;margin-bottom:20px;\">FAQ<\/h2>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\"><strong>Can I not simply take downtime cost from the maintenance system?<\/strong> The maintenance system gives you the work orders and the repair time, which is useful for the cost of maintenance itself. Short stops without a work order, and the time before the call and after the repair, are usually not in it. That is why it works best to combine the work orders with downtime measured at the machine.<\/p>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\"><strong>How long should I measure before choosing a strategy?<\/strong> Measure over a period that reflects normal production, for example a few weeks with your usual mix of products and shifts. Seasonal assets are best assessed during the peak season too.<\/p>\n<p style=\"font-size:17px;line-height:1.8;color:#232120;margin-bottom:20px;\"><strong>Is corrective maintenance still justified for some assets?<\/strong> Yes. When an asset is not critical, causes little measured downtime cost and is quick to repair, corrective maintenance can be the cheapest option, as long as safety and mandatory inspections allow it. Measurement makes that choice defensible.<\/p>\n<div style=\"background:#232120;color:white;padding:32px;border-radius:8px;margin:32px 0;text-align:center;\">\n<div style=\"font-size:18px;font-weight:bold;margin-bottom:8px;\">Your real OEE within days<\/div>\n<div style=\"font-size:14px;color:#ddd;margin-bottom:20px;\">Module wired in the electrical cabinet, sensor at the edge of the line, about one hour of installation per machine, no MES project and no production stop.<\/div>\n<p><a href=\"https:\/\/teeptrak.com\/fr\/demandez-une-demo\/\" style=\"display:inline-block;background:#EB352C;color:white;padding:14px 28px;text-decoration:none;border-radius:4px;font-weight:bold;\">Request a demo<\/a><\/div>\n<p><script type=\"application\/ld+json\">{\"@context\": \"https:\/\/schema.org\", \"@type\": \"FAQPage\", \"mainEntity\": [{\"@type\": \"Question\", \"name\": \"Can I not simply take downtime cost from the maintenance system?\", \"acceptedAnswer\": {\"@type\": \"Answer\", \"text\": \"The maintenance system gives you the work orders and the repair time, which is useful for the cost of maintenance itself. Short stops without a work order, and the time before the call and after the repair, are usually not in it. That is why it works best to combine the work orders with downtime measured at the machine.\"}}, {\"@type\": \"Question\", \"name\": \"How long should I measure before choosing a strategy?\", \"acceptedAnswer\": {\"@type\": \"Answer\", \"text\": \"Measure over a period that reflects normal production, for example a few weeks with your usual mix of products and shifts. Seasonal assets are best assessed during the peak season too.\"}}, {\"@type\": \"Question\", \"name\": \"Is corrective maintenance still justified for some assets?\", \"acceptedAnswer\": {\"@type\": \"Answer\", \"text\": \"Yes. When an asset is not critical, causes little measured downtime cost and is quick to repair, corrective maintenance can be the cheapest option, as long as safety and mandatory inspections allow it. Measurement makes that choice defensible.\"}}]}<\/script>[\/et_pb_text][\/et_pb_column][\/et_pb_row][\/et_pb_section]<\/p>\n","protected":false},"excerpt":{"rendered":"<p>[et_pb_section fb_built=&#8221;1&#8243; _builder_version=&#8221;4.27&#8243;][et_pb_row][et_pb_column type=&#8221;4_4&#8243;][et_pb_text] This article is for maintenance managers, engineering teams, plant managers and production managers who have to decide, asset by asset, whether to run corrective or preventive maintenance. You know the trade-off between criticality, downtime cost and safety. This article deals with the criterion that most often rests on an estimate: downtime [&hellip;]<\/p>\n","protected":false},"author":10,"featured_media":161692,"comment_status":"","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_yoast_wpseo_meta-robots-noindex":"","_yoast_wpseo_canonical":"","_et_pb_use_builder":"","_et_pb_old_content":"","_et_gb_content_width":"","ai_seo_title":"","ai_meta_description":"","ai_focus_keyword":"","footnotes":""},"categories":[129],"tags":[],"class_list":["post-165950","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-industrial-maintenance"],"yoast_head":"<!-- This site is optimized with the Yoast SEO plugin v28.9 - https:\/\/yoast.com\/product\/yoast-seo-wordpress\/ -->\n<title>Corrective or preventive maintenance: measure downtime cost<\/title>\n<meta name=\"description\" content=\"Choosing corrective or preventive maintenance needs downtime cost per asset. Here is how to measure it instead of estimating it, then classify.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/\" \/>\n<meta property=\"og:locale\" content=\"en_US\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Corrective or preventive maintenance: measure downtime cost\" \/>\n<meta property=\"og:description\" content=\"Choosing corrective or preventive maintenance needs downtime cost per asset. Here is how to measure it instead of estimating it, then classify.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/\" \/>\n<meta property=\"og:site_name\" content=\"TEEPTRAK\" \/>\n<meta property=\"article:published_time\" content=\"2026-11-25T08:39:31+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/11\/teeptrak-dts-en.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1600\" \/>\n\t<meta property=\"og:image:height\" content=\"900\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Alyssa Fleurette\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:creator\" content=\"@teeptrak\" \/>\n<meta name=\"twitter:site\" content=\"@teeptrak\" \/>\n<meta name=\"twitter:label1\" content=\"Written by\" \/>\n\t<meta name=\"twitter:data1\" content=\"Alyssa Fleurette\" \/>\n\t<meta name=\"twitter:label2\" content=\"Est. reading time\" \/>\n\t<meta name=\"twitter:data2\" content=\"7 minutes\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/\"},\"author\":{\"name\":\"Alyssa Fleurette\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#\\\/schema\\\/person\\\/c8f4c4c2953d0ad42f08de085e63529f\"},\"headline\":\"Corrective or preventive maintenance? Measure downtime cost per asset first\",\"datePublished\":\"2026-11-25T08:39:31+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/\"},\"wordCount\":1502,\"publisher\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/teeptrak.com\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/ttp-cover2-checklist-light.png\",\"articleSection\":[\"Industrial maintenance\"],\"inLanguage\":\"en-US\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/\",\"url\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/\",\"name\":\"Corrective or preventive maintenance: measure downtime cost\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/teeptrak.com\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/ttp-cover2-checklist-light.png\",\"datePublished\":\"2026-11-25T08:39:31+00:00\",\"description\":\"Choosing corrective or preventive maintenance needs downtime cost per asset. Here is how to measure it instead of estimating it, then classify.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/#breadcrumb\"},\"inLanguage\":\"en-US\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/#primaryimage\",\"url\":\"https:\\\/\\\/teeptrak.com\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/ttp-cover2-checklist-light.png\",\"contentUrl\":\"https:\\\/\\\/teeptrak.com\\\/wp-content\\\/uploads\\\/2026\\\/11\\\/ttp-cover2-checklist-light.png\",\"width\":1600,\"height\":900,\"caption\":\"TEEPTRAK illustration\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/corrective-preventive-maintenance-downtime-cost-per-asset\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Accueil\",\"item\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Corrective or preventive maintenance? Measure downtime cost per asset first\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#website\",\"url\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/\",\"name\":\"TEEPTRAK\",\"description\":\"Optimisez votre potentiel industriel\",\"publisher\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"en-US\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#organization\",\"name\":\"TeepTrak\",\"url\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/teeptrak.com\\\/wp-content\\\/uploads\\\/2026\\\/07\\\/TeepTrak_Logo-PNG-1-scaled.png\",\"contentUrl\":\"https:\\\/\\\/teeptrak.com\\\/wp-content\\\/uploads\\\/2026\\\/07\\\/TeepTrak_Logo-PNG-1-scaled.png\",\"width\":2880,\"height\":528,\"caption\":\"TeepTrak\"},\"image\":{\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"sameAs\":[\"https:\\\/\\\/x.com\\\/teeptrak\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/teeptrak\\\/\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/teeptrakinternational\\\/\",\"https:\\\/\\\/www.youtube.com\\\/@teeptrak\\\/videos\",\"https:\\\/\\\/www.instagram.com\\\/teeptrak\\\/\"]},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/teeptrak.com\\\/en\\\/#\\\/schema\\\/person\\\/c8f4c4c2953d0ad42f08de085e63529f\",\"name\":\"Alyssa Fleurette\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"en-US\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ac9dbd3bd4dd1699205324f9604e5cfe3ba1c748b1b7c2b2c06326350e48e966?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ac9dbd3bd4dd1699205324f9604e5cfe3ba1c748b1b7c2b2c06326350e48e966?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/ac9dbd3bd4dd1699205324f9604e5cfe3ba1c748b1b7c2b2c06326350e48e966?s=96&d=mm&r=g\",\"caption\":\"Alyssa Fleurette\"}}]}<\/script>\n<!-- \/ Yoast SEO plugin. -->","yoast_head_json":{"title":"Corrective or preventive maintenance: measure downtime cost","description":"Choosing corrective or preventive maintenance needs downtime cost per asset. Here is how to measure it instead of estimating it, then classify.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/","og_locale":"en_US","og_type":"article","og_title":"Corrective or preventive maintenance: measure downtime cost","og_description":"Choosing corrective or preventive maintenance needs downtime cost per asset. Here is how to measure it instead of estimating it, then classify.","og_url":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/","og_site_name":"TEEPTRAK","article_published_time":"2026-11-25T08:39:31+00:00","og_image":[{"width":1600,"height":900,"url":"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/11\/teeptrak-dts-en.png","type":"image\/png"}],"author":"Alyssa Fleurette","twitter_card":"summary_large_image","twitter_creator":"@teeptrak","twitter_site":"@teeptrak","twitter_misc":{"Written by":"Alyssa Fleurette","Est. reading time":"7 minutes"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/#article","isPartOf":{"@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/"},"author":{"name":"Alyssa Fleurette","@id":"https:\/\/teeptrak.com\/en\/#\/schema\/person\/c8f4c4c2953d0ad42f08de085e63529f"},"headline":"Corrective or preventive maintenance? Measure downtime cost per asset first","datePublished":"2026-11-25T08:39:31+00:00","mainEntityOfPage":{"@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/"},"wordCount":1502,"publisher":{"@id":"https:\/\/teeptrak.com\/en\/#organization"},"image":{"@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/#primaryimage"},"thumbnailUrl":"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/11\/ttp-cover2-checklist-light.png","articleSection":["Industrial maintenance"],"inLanguage":"en-US"},{"@type":"WebPage","@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/","url":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/","name":"Corrective or preventive maintenance: measure downtime cost","isPartOf":{"@id":"https:\/\/teeptrak.com\/en\/#website"},"primaryImageOfPage":{"@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/#primaryimage"},"image":{"@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/#primaryimage"},"thumbnailUrl":"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/11\/ttp-cover2-checklist-light.png","datePublished":"2026-11-25T08:39:31+00:00","description":"Choosing corrective or preventive maintenance needs downtime cost per asset. Here is how to measure it instead of estimating it, then classify.","breadcrumb":{"@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/#breadcrumb"},"inLanguage":"en-US","potentialAction":[{"@type":"ReadAction","target":["https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/"]}]},{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/#primaryimage","url":"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/11\/ttp-cover2-checklist-light.png","contentUrl":"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/11\/ttp-cover2-checklist-light.png","width":1600,"height":900,"caption":"TEEPTRAK illustration"},{"@type":"BreadcrumbList","@id":"https:\/\/teeptrak.com\/en\/corrective-preventive-maintenance-downtime-cost-per-asset\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Accueil","item":"https:\/\/teeptrak.com\/en\/"},{"@type":"ListItem","position":2,"name":"Corrective or preventive maintenance? Measure downtime cost per asset first"}]},{"@type":"WebSite","@id":"https:\/\/teeptrak.com\/en\/#website","url":"https:\/\/teeptrak.com\/en\/","name":"TEEPTRAK","description":"Optimisez votre potentiel industriel","publisher":{"@id":"https:\/\/teeptrak.com\/en\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/teeptrak.com\/en\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"en-US"},{"@type":"Organization","@id":"https:\/\/teeptrak.com\/en\/#organization","name":"TeepTrak","url":"https:\/\/teeptrak.com\/en\/","logo":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/teeptrak.com\/en\/#\/schema\/logo\/image\/","url":"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/07\/TeepTrak_Logo-PNG-1-scaled.png","contentUrl":"https:\/\/teeptrak.com\/wp-content\/uploads\/2026\/07\/TeepTrak_Logo-PNG-1-scaled.png","width":2880,"height":528,"caption":"TeepTrak"},"image":{"@id":"https:\/\/teeptrak.com\/en\/#\/schema\/logo\/image\/"},"sameAs":["https:\/\/x.com\/teeptrak","https:\/\/www.linkedin.com\/company\/teeptrak\/","https:\/\/www.linkedin.com\/company\/teeptrakinternational\/","https:\/\/www.youtube.com\/@teeptrak\/videos","https:\/\/www.instagram.com\/teeptrak\/"]},{"@type":"Person","@id":"https:\/\/teeptrak.com\/en\/#\/schema\/person\/c8f4c4c2953d0ad42f08de085e63529f","name":"Alyssa Fleurette","image":{"@type":"ImageObject","inLanguage":"en-US","@id":"https:\/\/secure.gravatar.com\/avatar\/ac9dbd3bd4dd1699205324f9604e5cfe3ba1c748b1b7c2b2c06326350e48e966?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/ac9dbd3bd4dd1699205324f9604e5cfe3ba1c748b1b7c2b2c06326350e48e966?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/ac9dbd3bd4dd1699205324f9604e5cfe3ba1c748b1b7c2b2c06326350e48e966?s=96&d=mm&r=g","caption":"Alyssa Fleurette"}}]}},"_links":{"self":[{"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/posts\/165950","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/users\/10"}],"replies":[{"embeddable":true,"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/comments?post=165950"}],"version-history":[{"count":0,"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/posts\/165950\/revisions"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/media\/161692"}],"wp:attachment":[{"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/media?parent=165950"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/categories?post=165950"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/teeptrak.com\/en\/wp-json\/wp\/v2\/tags?post=165950"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}